Here is a typical time line of a kitchen remodel by Kitchen Emporium
Week 1
Day 1- Tear out old cabinets, countertops, and appliances. Dispose of all debris.
Day 2- Remove walls, add walls, general carpentry
Day 3- Electrical rough in. Add, remove or change any electrical. Most jobs require 1 day.
Day 4- Relocate any plumbing if needed.
Day 5- Plaster work. Make all wall and ceiling repairs. Usually requires a return trip to touch up.
Week 2
Day 1-5- Cabinets are installed. Some kitchens will be quicker than others depending upon the size of the kitchen.
Day 3,4 or 5- Measure for countertops.
Week 3
Floor installation may be installed at this time.
Week 4
Countertops may be installed this week. During extremely busy times, they may take another week. Once installed, we will schedule the electrician and plumber to connect all plumbing and electrical fixtures.
Week 5
Day 1- Install tile back splash
Day 2- Make any adjustments to cabinets, countertops, plaster touch up and paint touch up.
Week 6
Finish anything that did not get done in week 5.
The above time line is very typical of a kitchen remodel by Kitchen Emporium, however there are situations that cannot be planned for and will be the cause for deviation from the schedule. We will do all within our power to adhere to this schedule, but please do not refer to this schedule as the exact schedule for your kitchen remodel. We will do our best to give you your new kitchen in the shortest amount of time without sacrificing the quality of work.
October 15, 2015 at 2:01 AM
Wow..!!! it is very nice.. I am really interested with it… thankyou so much…All Wood Cabinets Tampa bay
January 13, 2016 at 12:22 AM
Wow…!! It’s very interesting… I am really impressed with your post.. Thanks for sharing it..
http://www.kbfactoryoutlet.com/
Kitchen countertops